Kier Transportation is searching for sub-contractors to fill £84M worth of works on the £500M A417 “missing link” scheme, including earthworks, drainage and pavements.
The £500M scheme for National Highways will dual a 5.5km section of road between Gloucester and Swindon, improving the connection between the two dual carriageway sections of the A417 at Brockley and Cowley and the connection between the M4 and M5.
Main contractor Kier Transportation, which won the £460M contract in April 2022, has published 15 contract notices for sub-contractors to join the project.
The most lucrative contract is for £35M worth of earthworks. There is also an £18M opportunity for drainage works and a £15M pavement works contract up for tender.
All 15 contracts are detailed below in order of value.
Interested parties can make contact with guy.hornsey@kier.co.uk to register their interest. There are several different deadlines for expressions of interest, with the earliest coming later this month.
Works | Value | Delivery | Expression of interest deadline |
Earthworks | £35M | 11 Mar 2024 to 28 Aug 2026 (29.5 months) | 29 Feb |
Drainage | £18M | 15 Apr 2024 to 28 Aug 2026 (28.5 months) | 29 Feb |
Pavement | £15M | 27 Aug 2024 to 02 Oct 2026 (25 months) | 17 May |
Structures, formwork, reinforcement and concrete | £5M | 20 Mar 2024 to 02 Dec 2026 (32.5 months) | 31 Jan |
Steelwork and steel parapets | £4M | 2 Sep 2024 to 31 Oct 2024 (Two months) | 31 Jan |
Pre-cast concrete parapets, culverts, wing walls, headbeams, headwalls and pre-stressed beams | £2M | 17 Dec 2024 to 15 Jul 2026 (19 months) | 31 Jan |
Prefabricated vertical drains | £2M | 04 Apr 2024 to 14 Mar 2025 (11.5 months) | 16 Feb |
TASCAR (traffic automated speed cameras) | £0.85M | 3 Jun 2024 to 24 Dec 2026 (30.5 months) | 26 Jan |
Vehicle recovery services | £0.8M | 3 Jun 2024 to 24 Dec 2026 (30.5 months) | 15 Mar |
Temporary CCTV | £0.5M | 3 Jun 2024 to 24 Dec 2026 (30.5 months) | 16 Feb |
Structures timber parapets | £0.3M | 24 Feb 2025 to 24 Feb 2026 (12 months) | 31 Jul |
Horizontal directional drilling (utility diversion) | £0.25M | 16 Apr 2024 to 16 Aug 2024 (four months) | 26 Jan |
Instrumentation and monitoring / Surface and ground water monitoring | £0.2M | 12 Feb 2024 to 13 Feb 2026 (24 months) | 26 Jan |
Structures bridge bearings | £0.04M | 30 Jul 2024 to 19 Aug 2024 (20 days) | 2 Feb |